This tiny remark on October 17, 2012 at Senate Estimates has set off all sorts of interesting commentary.
“Senator FIERRAVANTI-WELLS: What is the status of the National Authentication Service for Health?
Mr Fleming : As you are probably aware, we did terminate the contract with IBM. We have been working with DOHA and DHS. We have implemented a NASH solution with DHS, which is in operation and rolling out. That is progressing.
Senator FIERRAVANTI-WELLS: When will this be complete?
Mr Fleming : NASH is doing what we need now. For PCEHRS there is a second component which will support secure messaging. DHS is working with some final phases there, and they will make some announcements in the very near future. Certainly everything we need NASH to do it is capable of and it is doing.”
For some reason it took till the next week for the story to take off despite the fact it had been common knowledge for months that NASH was a real mess.
This September 6, 2012 blog makes it clear what IBM was doing was in grave trouble.
This is the most comprehensive discussion I have seen.
IBM’s NASH deal gets terminated
news The National E-Health Transition Authority and IBM this afternoon confirmed Big Blue’s $23.6 million contract to build a key component of the Federal Government’s Personally Controlled Electronic Health Record project had been “terminated”, just 18 months after the contract was initially inked. However, it is unclear where culpability lies in the situation.
As part of a $466.7 million investment in the e-health records announced in September 2010 by the Federal Government, the nation’s peak e-health body NEHTA chose IBM in March 2011 to build and manage its new National Authentication Service for Health (NASH) system, which aims at establishing a nationwide secure and authenticated service for both healthcare organisations and personnel that have to exchange e-health information.
At the time, NEHTA chief executive Peter Fleming said NASH would improve healthcare for both professionals and patients. “Our agreement with IBM enables NEHTA to build a system that will give healthcare professionals timely and secure access to appropriate patient information,” he said in a statement. “In turn, the NASH program will take us one step closer to broader healthcare access for all Australians.”
The contract was to allow IBM to manage the delivery of the NASH project, offering its hardware, software and services capabilities which include assistance, security and access management technologies, as well as IT infrastructure management.
IBM Australia and New Zealand managing director Andrew Stevens said at the time that the delivery of the NASH would establish a more patient-centric healthcare system, while improving health outcomes for Australians. “This program will benefit over 600,000 Australian doctors, nurses and allied health providers and accelerate the delivery of smarter healthcare across the entire healthcare system,” he said.
The transition from existing healthcare systems was to have been ensured by the deployment of a software development kit (SDK) to be provided by NEHTA, which the authority said would guarantee transactions are authenticated and audited in accordance with Australian standards. Once functioning, NEHTA said the NASH would deliver clinical terminology, messaging standards, unique health identifiers and would become one of the fundamental building blocks for a national e-health system.
Lots more here:
Additionally there is some useful background here:
IBM loses key e-health contract
Human Services steps in as provider.
The National E-Health Transition Authority (NEHTA) has sacked IBM as provider of the National Authentication Service for Health (NASH) after it failed to deliver the service on time.
The NASH service designed and built by IBM was intended to provide a secure means for clinicians to connect with the Federal Government’s $467 million Personally Controlled Electronic Healthcare Record (PCEHR) system.
IBM won the $23.6 million NASH contract in March 2011 and was due to deliver the system on 26 June 2012.
Lots more here:
This paragraph of commentary on the overall PCEHR program is also of interest from the Delimiter article mentioned above:
“opinion/analysis
It’s hard to say what’s really going on here, as I don’t have much knowledge of what’s happening between IBM and NEHTA behind the scenes. However, as someone who’s kept an eye on NEHTA over much of the past decade, I have to say that I don’t have a huge amount of confidence in the organisation or the delivery of the PCEHR in general. NEHTA has suffered a number of communication and delivery problems in the past, and the e-health records area is incredibly complex and notoriously hard to navigate. There have been reports of problems with the PCEHR for months and months now, and I wouldn’t be surprised to hear that the project as a whole is gradually going off the rails.”
It’s hard to say what’s really going on here, as I don’t have much knowledge of what’s happening between IBM and NEHTA behind the scenes. However, as someone who’s kept an eye on NEHTA over much of the past decade, I have to say that I don’t have a huge amount of confidence in the organisation or the delivery of the PCEHR in general. NEHTA has suffered a number of communication and delivery problems in the past, and the e-health records area is incredibly complex and notoriously hard to navigate. There have been reports of problems with the PCEHR for months and months now, and I wouldn’t be surprised to hear that the project as a whole is gradually going off the rails.”
It is interesting to read Renai LeMay express this level of concern regarding the overall project and also rather refreshing given the lack of other commentary in the last few months. The utility of independent commentary is clearly seen here as the views expressed are much the same as I hear virtually every other day,
In this context and in the light of this recent comment from Eric Browne one wonders what is actually working
Australian Medicines Terminology browser update
2012-October-03 | 21:52 By: eric
Healthbase Australia has updated the online Australian Medicines Terminology browser to include the 2.36 version of the AMT released by NEHTA today. All deprecated versions are still available for browsing/searching.
It would be useful to hear from any organisation that has implemented, or tried to implement a clinical system based on the AMT, despite its current shortcomings. After all these long years, we are still not aware of any organisation that has a proper deployment where current AMT data is being shared and used by other systems!!
The note is here:
From the ePIP requirements we know that coding has not been standardised - despite all the work on SNOMED-CT over the years as well and I am also told some trying to use the Health Identifier Service are having problems getting reliable results.
Despite the recognised need for an End Point Location Service for the Secure Messaging Service this is still also being developed.
All in all for all that has been invested in NEHTA and the NEHRS Program this is really looking like gross underperformance.
I wonder what will now happen with the funding cuts etc. that we know have happened but not yet been announced. Even slower delivery?
David.